List what must keep running and check the announced window. Then bridge it with a rented generator, your own generator or a battery system. A battery takes over without a gap and can also switch back cleanly. Our guide to the right emergency power supply for your business compares UPS, generator and battery in general. This article applies it to the cut you know is coming. A battery that only waits for that one day rarely pays. Business battery systems that also shave your peak and store solar power every day do.
You probably know one of these two moments. A letter or a text message from the grid operator: next Tuesday, from 8:00 to 16:00, no power in your street. Or the maintenance company asks when it can switch off your high-voltage cabin for the yearly inspection. Either way, somebody else picks the hours, and your site stops.
What is easy to underestimate is the restart, not the cut itself. Cold rooms need hours to come back to temperature. A production line that stopped mid-batch loses the batch. Servers that went down hard need someone to check them. And a generator rented at the last minute only helps if an electrician can connect it safely.
A site in Maasmechelen shows another way. The customer already had a generator for emergencies, but it stood idle. Our semi off-grid system made it useful: the customer chooses the grid or the generator to charge its own off-grid system. The system has 24 kVA of inverter power and 30.8 kWh of battery.
What is a planned power interruption, and how much notice does a business get?
A planned power interruption is a cut the grid operator announces in advance, usually for works on the grid in your area. Fluvius says it announces them beforehand. The Flemish technical regulation (TRDE) sets the minimum notice.
| Your connection (Flanders) | Minimum notice | What else the rule says |
|---|---|---|
| Low voltage | At least 5 working days | Also to your supplier if it asked for it |
| Medium or high voltage | At least 10 working days | The grid operator interrupts after consultation with you |
| Emergency or restoring normal operation | No minimum | Notice rules do not apply |
Source: Vlaamse Nutsregulator, Technical regulation for electricity distribution, version 2026, articles 2.3.4 and 2.3.5. Read the full text of the TRDE.
Three practical points follow from the Fluvius FAQ. A planned interruption can usually not be moved at your request, because the works are planned in detail. You are usually not without power for the whole announced window. And you can get a text message or e-mail about interruptions on your address.
In Wallonia, the Walloon technical regulation also requires advance notice, longer for high voltage than for low voltage. ORES adds a useful promise: it provides a generator when a planned cut would last more than 4 hours, unless that is technically impossible. In Brussels, Sibelga publishes its planned interruptions on its website.
Tip
Register your site for the alerts of your grid operator, and give them a number that is answered. Five working days is short to rent a generator, find an electrician and warn your customers.
Why does maintenance of your own high-voltage cabin mean a power cut?
Because the law asks a yearly check of your cabin, and the cabin must be able to go dead for it. The AREI (the Belgian electrical code), Book 2 on high-voltage installations, requires a yearly control visit by an approved inspection body after the first inspection.
The same text says the installation must be able to be switched off during that visit. The inspection body Atlas Contrôle gives an average duration of 2 to 4 hours for the yearly verification. It covers tests of the protections, insulation measurements, the earthing and the disconnectors.
When the cabin is switched off, everything behind it is off: offices, production, cooling, lighting and alarms. Cleaning, repairs and a transformer swap can take longer than the inspection. The difference with a grid interruption is that you choose the day, together with your maintenance company.
Are you still deciding whether you need a cabin at all? Then read our article on a high-voltage cabin versus a battery. Is your transformer too small for what you plan? Our article on a transformer that is too small weighs a new one against a battery behind it.
Watch out
Only warned (BA4) or skilled (BA5) persons may enter and operate a high-voltage room. Let the switching off and on be done by a qualified high-voltage technician, never by staff on their own.
What stops at your site when the power goes, and what does it cost?
Start with a list of loads, not with a machine. Some loads can simply wait. Others lose money, stock or safety within minutes. That list decides how big your bridge must be.
| Load | What happens without power | Keep it running? |
|---|---|---|
| Cold rooms and freezers | Temperature rises; stock at risk after a few hours | Yes, or precool and keep doors shut |
| Servers, network, PLCs and controls | Hard shutdown, data loss, restart checks | Yes, at least for a clean shutdown |
| Production lines and ovens | Batch lost, long restart | Often better to plan the stop |
| Barn ventilation and feeding | Animal welfare at risk quickly | Yes |
| Alarms, access control, cameras | Site open or unmonitored | Yes, they draw little |
| Offices, workshop, charging points | Work stops, but nothing breaks | Usually not |
For cold rooms, our article on how long a battery keeps a cold room cold gives the calculation. For livestock, read how to keep barn ventilation running in a power cut. For IT, a UPS often covers a clean shutdown: our article on which inverter or UPS a business needs explains the difference.
Rented generator, own generator or battery: what keeps your site running during a planned cut?
For a single cut once in a while, a rented generator is often enough. When cuts or shutdowns return, and the loads cannot miss a second, a battery system or a battery with a generator is the robust answer.
| Option | Switchover | Good for | Watch out for |
|---|---|---|---|
| Rented mobile generator | Site goes off, then on the generator | One announced cut or one shutdown | Needs a prepared connection point and an electrician; delivery and fuel on time |
| Own standby generator with automatic switch | A few seconds without power | Long cuts, if it is maintained | Compressors and IT drop out at the switch; test it under load |
| Battery system with island function | Within milliseconds | Cuts of a few hours; clean switch back | Capacity limits a long window |
| Battery plus generator that starts automatically | Within milliseconds, generator later | Long windows, and unannounced cuts too | Highest investment, most robust |
According to Victron, a MultiPlus-II takes over in less than 20 milliseconds, fast enough to keep computers running. A Victron GX controller can start a generator automatically, for example when the battery gets low. In Maasmechelen, the idle emergency generator became a charger for the battery. Our article on combining a generator with a battery explains how the two share the work.
The same idea works at a smaller scale. At a home in Maaseik, a generator was already there. The battery system got an off-grid mode, so the generator can be connected to it.
How do you switch over to back-up power safely, and back to the grid?
The golden rule: your back-up source must never feed power back into the grid or into a cabin where people are working. A proper changeover separates your installation from the grid before the back-up source takes over.
What happens on the day of a planned cut
Switching back is the moment many sites forget. With a simple changeover switch, your site goes dark for a moment again when the grid returns. The Synergrid rule C10/11 allows an emergency supply system to run in parallel with the grid only briefly: at most 5 minutes per switchover. Every parallel connection must be recorded in a logbook.
A planned cut from 8:00 to 16:00
Important
Never improvise a connection with a plug that has pins on both ends, or by bridging phases. A generator connected this way can put voltage on the grid where technicians are working, and on the plug pins in your hand. Let an electrician install a proper inlet and changeover switch.
Watch out
Your solar panels stop during the cut. C10/11 requires grid-connected installations to disconnect automatically when the grid fails. They only keep producing when a battery system forms a local grid for them.
How big must a battery be to bridge a planned power interruption?
Multiply the average power of your critical loads (kW) by the hours of the announced window, and add a margin. 15 kW of critical loads over 4 hours needs about 60 kWh of usable energy.
Usable battery energy needed for 15 kW of critical loads
Two things set the size. Energy (kWh) sets how long the battery lasts. Power (kVA) sets whether everything can start at once. Motors and compressors draw several times their running current for a few seconds. So measure the loads, rather than adding up nameplates.
An 8-hour window at 15 kW needs 120 kWh. For that, a generator as second line is usually more logical than a battery twice as large. In a Victron system you keep a fixed reserve in the energy management (ESS). The battery only goes below it when the grid fails. Above that reserve, it shaves peaks and stores solar power.
Want to know what your critical loads draw and how long a battery can carry them? Call us or send a message.
What should you do before a planned power interruption?
Treat a planned cut like a small project with a checklist. Five working days is enough if you start on day one.
- Step 1: Read the notice and confirm the window. Note the date, start, expected duration and the reference, and ask the grid operator if the window is unclear.
- Step 2: List the critical loads and decide what may stop. Plan production, deliveries and cleaning around the window.
- Step 3: Arrange the bridge. Rent the generator or check your own, test the battery reserve, and book the electrician who will switch over.
- Step 4: Protect stock and data. Precool cold rooms, keep doors shut, save work and shut down servers you do not keep on.
- Step 5: Open what needs power to open. Automatic gates, roller doors and barriers stay shut without power.
- Step 6: Restart in order. Switch heavy loads on one by one, check the cold rooms and servers, and reset clocks and timers.
Fluvius gives similar tips: avoid lifts, keep fridges and freezers closed, save your work and open automatic gates beforehand.
Can your business claim compensation for a planned power interruption?
Usually not. The Flemish compensation for long cuts only applies to unplanned interruptions of more than 4 hours. The cut may not have been announced in advance. What a business can claim after an unplanned cut is explained in what your company can claim after a power cut.
For a business the Flemish compensation for such an unannounced cut is 20% of last month's distribution costs, with a minimum of 35 euro. ORES compensates cuts of more than 6 hours that were not announced beforehand and were not caused by force majeure.
The trade magazine Buurtsuper warns that compensation for a planned cut is uncertain. The grid operator is only liable when the cut was no emergency and the notice came late or was deficient. So check your own insurance for damage from planned and unplanned cuts. The load-shedding plan is a separate case: our article on what a company should do about a blackout in Belgium explains it.
When is a battery not worth it for planned power cuts?
When it would only wait for one announced cut a year.
Our verdict
Take a workshop with one cabin inspection a year and nothing that cannot stop. It is better off planning that inspection on a quiet day, or renting a generator. A battery earns its place when it also works on normal days: shaving the quarter-hour peak, storing solar power or saving a heavier connection. Then the planned cut, and the unannounced one, come almost free.
Our article on what peak shaving is and when a battery pays off shows that daily work. The back-up is the bonus.
What happens when you ask us to bridge planned cuts at your site?
We start with what must keep running and what it really draws.
- Step 1: Analysis and sizing. We list the critical loads and their starts. If data is missing, we can monitor your consumption for a short period first.
- Step 2: Technical design. We choose the reserve, the inverter power, the changeover and, where useful, an automatic generator start or a connection for a rented one.
- Step 3: Installation and commissioning.
- Step 4: Monitoring and support. You follow the state of charge and consumption in the app and the VRM portal.
Our battery systems for businesses range from small SME installations to modular systems up to 1 MW. Our monitoring software shows what your site draws, also during a cut.
Frequently asked questions
Can the grid operator cut my power without warning?
Yes, in an emergency. The notice rules in the Flemish technical regulation do not apply to urgent works after an emergency or to restore normal operation. That is why a back-up for announced cuts is also worth something on the day nobody warned you.
Who may switch my high-voltage cabin off and on?
Only warned (BA4) or skilled (BA5) persons may operate in a high-voltage room. In practice, your maintenance company or a qualified high-voltage technician does the switching.
Is a UPS enough for a planned power cut?
For a clean shutdown of servers, yes. A UPS is built to bridge minutes, not a working day. For a window of several hours you need a battery system with more energy, or a generator.
Should the whole site be on the back-up during the cut?
Usually not. Put cooling, IT, controls and alarms on the backed-up circuits and let offices, workshops and chargers wait. The reserve then lasts much longer.
How do I know when a planned interruption is coming?
Through the letter or message from your grid operator, and on their websites: Fluvius, ORES and Sibelga all publish planned interruptions. Sign up for alerts with the address of your site.
Want your site to keep running during the next planned cut?
Tell us what must keep running, what it draws and how long the announced cuts or shutdowns last. One of our engineers will tell you whether a battery, a generator or both make sense. You will also know what the same system saves on the other days.
Sources
- Vlaamse Nutsregulator: Technical regulation for electricity distribution (TRDE), version 2026
- Fluvius: frequently asked questions on interruptions
- Fluvius: power interruptions and alerts
- Flemish government: compensation from grid operators for late reconnection and power interruption
- ORES: planned and unplanned interruptions
- Sibelga: planned power interruptions
- AREI Book 2, installations on high voltage (chapter 6.5, control visits)
- Atlas Contrôle: inspection of a high-voltage cabin
- Buurtsuper: planned power interruption and risks (2026)
- Synergrid: technical prescription C10/11, edition 2.4
- Victron Energy: MultiPlus-II
- Victron Energy: GX generator auto start/stop
- Victron Energy: ESS manual