It depends on where your building is and how many car spaces its car park has. In Flanders an existing non-residential building with more than 20 spaces needs at least two charging points. In Wallonia it needs one, plus ducting for 1 space in 5. In Brussels a permitted car park needs a share of its spaces equipped, up to 30% for offices by 2035. The minimum is small today, but it grows fast. Load management, and where needed a business battery that covers the charging peaks, lets you meet it on the connection you already have.
Maybe you manage an office, a shop or a warehouse with a car park. Staff are switching to electric company cars. The landlord, a customer or an auditor asks whether the site is compliant. And the electrician says the connection will not carry many chargers.
What most owners do not see yet is that the minimum is a moving target. Two charging points is what Flanders asks today. The European directive asks ten for a car park of 100 spaces from 2027, and Brussels already goes further. A logistics entrepreneur on a Belgian forum wrote that he had waited over a year for a Fluvius connection. It was for his solar and charging project. Wait for the next rule change and you join that queue.
There is another route. On a farm in Tielt, the battery system delivers extra power, so the connection did not need to be upgraded. The grid stays connected, but only as a charger.
Which business buildings must have charging points in Belgium?
Every non-residential building with a car park above a threshold must have charging points or ducting, and the threshold depends on the region. The rules come from the European directive on the energy performance of buildings. Each region wrote its own version.
| Region | New building or major renovation | Existing building |
|---|---|---|
| Flanders | Car park with more than 10 spaces: at least 2 charging points and ducting for 1 space in 4 (permit applied for from 11 March 2021) | Car park with more than 20 spaces: at least 2 charging points since 1 January 2025 |
| Wallonia | More than 10 spaces: 1 charging point and ducting for 1 space in 5 | More than 20 spaces: 1 charging point and ducting for 1 space in 5 since 1 January 2025 |
| Brussels | Permitted car park (from 10 spaces): offices 30% of spaces, other car parks 20%, immediately | Offices 10% in 2025, 20% in 2030, 30% in 2035; public and other car parks 5%, 10%, 20% |
| EU directive (by 1 January 2027) | More than 5 spaces: 1 charging point per 5 spaces (offices 1 per 2) and pre-cabling for half the spaces | More than 20 spaces: 1 charging point per 10 spaces, or ducting for half the spaces |
Sources: Vlaanderen.be, SPW Energie (energie.wallonie.be), Bruxelles Environnement and Directive (EU) 2024/1275, article 14. Links in the sources list.
A charging point is more than a socket. In Flanders it must deliver more than 3.7 kW (16 A) and have a Type 2 (AC) or Combo 2 (DC) connector. The rules cover spaces for passenger cars, not trucks or tractors. If you plan to charge trucks, read our article on charging electric trucks at your depot.
What does Flanders require for charging points at non-residential buildings?
In Flanders, an existing non-residential building with more than 20 parking spaces needs at least two charging points since 2025. New buildings and major renovations with more than 10 spaces need two charging points and ducting for 1 space in 4.
A major renovation here means that more than 25% of the building envelope is renovated. The duty then applies when the works also touch the car park or the electrical installation. Ducting means conduits or cable trays, so a charging point can be added later without breaking open the car park.
The details decide how many points you need:
- The rule applies per car park. Zones reached through one access road count as one car park. Car parks with their own access road are counted separately.
- One car park for several buildings adds up. Vlaanderen.be gives the example of a supermarket and a shoe shop on one car park: at least four charging points since 2025.
- Adjacent car parks count. A car park on your own site, used by the building users, falls under the rule.
- Public access is your choice. The rules do not say whether the charging points must be open to the public.
- Agricultural and industrial buildings are non-residential too. A farm or factory with a large car park is covered.
The building owner is responsible, or the holder of a real right such as a long lease. For a new building it is the permit holder. The Flemish energy agency VEKA can fine 2,000 euro per missing charging point and 1,000 euro per space without the required ducting. For a major renovation, the duty is capped at 7% of the total renovation cost.
Watch out
Renting the building? The duty lies with the owner, but who pays and who owns the chargers belongs in the lease. Our article on a battery in a rented business building covers what the lease should say about installations like these.
What are the charging point rules in Wallonia?
In Wallonia, a non-residential building with more than 20 spaces has needed one charging point and ducting for 1 space in 5 since 2025. New buildings and major renovations with more than 10 spaces carry the same duty.
The Walloon rule is part of the energy performance rules (PEB). A major renovation means works on at least a quarter of the envelope. Several separate car parks serving one building are added up to check the threshold. Buildings for collective housing, such as care homes, follow the non-residential rule.
A car park counts as adjacent when three conditions are met. It is physically or technically connected to the building. It is used mainly by the building occupants. And the same holder of a real right owns both. Planning a connection or a heavier one in Wallonia? Our article on grid tariffs for businesses in Wallonia and Brussels explains what peaks cost with ORES, RESA and Sibelga.
How many charging points does a Brussels car park need?
In Brussels, the number of charging points follows the number of spaces in your environmental permit and the type of building. It applies to car parks from 10 spaces, covered or in the open air.
| Car park type | 2025 | 2030 | 2035 | New car park |
|---|---|---|---|---|
| Offices | 10% (at least 2) | 20% | 30% | 30% |
| Public use or other | 5% (at least 2) | 10% (at least 2) | 20% | 20% |
| Residential | 1 point per resident space with an electric car, on request |
Fast charging counts extra. A charging point from 50 to 150 kW counts as 5 points, and one of 150 kW or more counts as 10. In a covered car park, fast chargers above 50 kW need explicit permission in the permit. The fire service must give a positive opinion first. Mixed car parks apply the ratios pro rata, and shared spaces take the highest ratio.
Brussels adds safety and reporting duties. You declare the installed charging points to the grid operator every year. You need an emergency stop at each entrance and a fire-resistant surface under the chargers. New car parks must provide ducting for a charging point on every space and a technical room for a high-voltage cabin. Where compliance is technically impossible or too expensive, you can ask for a reasoned exemption.
Minimum charging points for an existing office car park with 100 spaces
What changes for charging points in 2027 with the European buildings directive?
By 1 January 2027, the revised European directive asks one charging point per 10 spaces, or ducting for half of them. It covers every non-residential building with more than 20 spaces. Today's Flemish and Walloon minimum is far lower.
Directive (EU) 2024/1275 had to be transposed by 29 May 2026. At the time of writing, in September 2026, the official Flemish and Walloon pages still show the 2025 rules. Plan for the European level anyway: it is the floor the regions must reach.
- New or renovated, more than 5 spaces: 1 charging point per 5 spaces, plus pre-cabling for half the spaces and ducting for the rest.
- New and renovated office buildings: at least 1 charging point per 2 spaces.
- Bicycles: parking for at least 15% of the average or 10% of the total user capacity of the building.
- Buildings owned or used by public bodies: pre-cabling for half of the spaces by 1 January 2033.
- Smart charging: the charging points must be capable of smart charging and, where appropriate, bidirectional charging.
The directive also asks that pre-cabling is sized for the simultaneous use of the required charging points. It mentions load management explicitly. That matters for your connection: 30 charging points on a new office car park of 60 spaces are 330 kW on paper.
Flanders is also preparing its own step. According to Fleet.be (August 2026), a draft decree would require every new or replaced private charging point to support smart charging from 1 January 2028. It is a draft, not yet law.
Designing a new building? Our guide for architects and engineering firms designing a building with a battery shows how to plan chargers, board and battery together.
How much power do the required charging points add to your connection?
On paper, every AC charging point adds 11 kW on three phases at 16 A, or 22 kW at 32 A. Two points are 22 kW. Ten points are 110 kW when all cars charge at full power at the same time.
Two charging points usually fit on the connection of a business building. The problem starts with the next steps: the Brussels ratios, the European level from 2027, and the employees who all want to charge. Ten or thirty charging points can push a building past the limit of its connection.
In Flanders, that limit has consequences. Fluvius connects everything below 25 kVA on low voltage. Between 25 and 250 kVA the grid operator decides. Above 250 kVA you are always connected on medium voltage, with your own customer cabin. From 25 kVA, a paid study comes first. In areas with congestion, the connection can also be postponed. Our article on what to do when a heavier connection is refused covers that case.
Real demand is lower than the sum on paper, because cars arrive at different times and with different states of charge. To work out your real extra power from simultaneity and quarter-hour data, read our article on charging stations for a business without a heavier connection. Every extra kW in your monthly peak also costs money through the capacity tariff for businesses.
Tip
In Flanders you must register a private charging point of 5 kVA or more with Fluvius, via Mijn Fluvius. That duty has applied since June 2021, whatever the number of charging points.
How do you meet the charging point obligation without a heavier connection?
Install the required charging points and let them share the power your connection has left. Add a battery only where cars and building peak at the same time. In that order, most business buildings meet the rule without a new connection.
From charging point obligation to a site that complies
Place the ducting for the next step now
Conduits for later charging points cost little while the car park is open. Size them for the European level, not for today's minimum.
Use load management on every charging point
The chargers measure the power at the connection and slow down when the building needs it. Cars that stay parked all day or all night charge fully anyway.
Add a battery where the peaks coincide
When cars charge while the building runs at full power, the battery supplies the difference. It recharges when there is room, or from solar panels.
Keep fast chargers for real needs
A DC fast charger counts extra in Brussels, but it also adds tens of kW at once. Without a buffer it goes straight into your peak.
A battery does this automatically. In a Victron system, the peak shaving limits apply to the complete system, including EV chargers installed in parallel. Above the limit, the battery supplies the extra power, as long as it has enough charge. Our business battery systems support fast-charging infrastructure, with chargers up to 180 kVA controlled via Victron technology. Read how peak shaving with a battery works in practice.
From practice
In Wingene, a semi off-grid site runs on a battery system of 150.4 kWh with 45 kVA. It delivers 3 x 400 V 63 A from the battery alone. Solar panels, or a wind turbine, add their power to that, so no medium voltage is needed. The new electric car will charge bidirectionally, so it can support the battery when energy runs short.
When is a heavier connection or a cabin still the better choice?
When your extra demand stays above the connection limit for hours every day. A battery shifts energy; it cannot deliver energy that is not there.
Our verdict
Think of a site where 50 cars charge fully every working day while production runs at full power. No battery of a reasonable size fills that gap all day. Ask for the heavier connection or the cabin, and use load management to keep it as small as possible. Our article on a medium voltage cabin or a battery compares both routes.
Buying or renting a new business building? Check the grid connection before you sign, including the car park and the charging points the new rules will ask.
Want to know how many charging points your car park needs, and whether your connection can carry them? Call us or send a message.
What happens when you ask us to check your car park?
We start from your car park, your region and your measured consumption.
- Step 1: Count. We list your car parks, spaces and building type, and the rule and deadline that apply to each.
- Step 2: Measure. We compare your quarter-hour peak with the limit of your connection. If data is missing, we measure first.
- Step 3: Design. We size charging points, load management and, where the peaks coincide, a battery with its inverter power.
- Step 4: Install and follow up. Installation, commissioning, inspection under the electrical code (AREI) and monitoring in our software.
A battery system on your site needs its own checks, such as fire safety and the notification to the grid operator. Our article on business battery safety covers fire service, permits and insurance.
Frequently asked questions
Does an employer have to provide charging points for staff?
Not as an employer. The duty is attached to the building and its car park. The owner of a non-residential building above the threshold must provide it.
Do the required charging points have to be open to the public?
In Flanders, no. The rules leave it to you whether the charging points are public or reserved for staff and visitors.
Do spaces for trucks or tractors count?
No. In Flanders the rules apply to spaces for passenger cars only. Truck charging is a separate question of power and planning.
Does one DC fast charger replace several AC charging points?
In Brussels, a charging point of 50 to 150 kW counts as 5 points, and one of 150 kW or more as 10. In Flanders and Wallonia the minimum is a number of charging points; check the text of your region before you count.
What happens if the grid operator cannot give us more power?
Then load management and a battery are the way to add charging points on the existing connection. In Brussels you can also ask for a reasoned exemption when compliance is technically impossible or too expensive.
Want to meet the charging point rules without waiting for a heavier connection?
Tell us where your building is, how many spaces your car park has and what your connection is. One of our engineers will tell you what the rules ask, now and from 2027. And how to add the charging points on the power you have.
Sources
- Vlaanderen.be: obligations for charging points at car parks (NL)
- SPW Energie: PEB and electromobility requirements from 1 January 2026 (FR)
- Bruxelles Environnement: covered and underground car parks, charging point ratios (FR)
- Bruxelles Environnement: open-air car parks (FR)
- EUR-Lex: Directive (EU) 2024/1275 on the energy performance of buildings, article 14
- Fluvius: mandatory registration of a private charging point (NL)
- Fluvius: customer requests and connection tariffs 2026 (NL, PDF)
- Victron Energy: peak shaving for ESS, limits for the complete system
- Fleet.be: Flanders prepares a decree on smart charging points from 2028 (NL)