How do you read the Fluvius grid congestion map in Belgium?

Orange, yellow or green on the Fluvius congestion map: what each colour means for your expansion, who it applies to, and what ORES and Sibelga tell you instead.

How do you read the Fluvius grid congestion map in Belgium?

Look up your area on the monthly Fluvius map: orange means only flexible connections, yellow flexible from 1 MVA, green classic. In Belgium only Flanders publishes such a grid congestion map, for medium voltage from 100 kVA. On low voltage, a semi-off-grid system often keeps you on your street connection.

You are planning a new hall, a heat pump or a row of chargers. The bank, the architect or a supplier says: "Check the congestion map first." You open it and almost all of Flanders is orange. Is the grid full where you are?

Which grid congestion map applies to companies in Belgium?

In Flanders, the Fluvius congestion map is the public map for business connections. Wallonia and Brussels do not publish a comparable colour map. Other maps in search results answer other questions.

Map What it shows Useful for your expansion?
Fluvius congestion map (Flanders, monthly)Connection options for high and very high power per area fed by one transformer stationYes: the starting point in Flanders
Elia Congestion Risk Indicator (open data)The risk of congestion per electrical zone, hour by hourNo: it is about running the grid, not about new connections
ORES map of inverters that trip (Wallonia)Neighbourhoods where the voltage runs too high because of solar panelsNo: it is about solar injection at homes
Capacity maps from the NetherlandsAvailable capacity on the Dutch gridsNo: they do not cover Belgium

Belgian companies connected directly to the high-voltage grid deal with Elia, not with Fluvius.

Watch out

Older articles mention a Fluvius "capaciteitswijzer" per parcel, launched in January 2024. Fluvius now points to the monthly congestion map instead.

What does the Fluvius congestion map show, and does it apply to you?

The map shows, per power supply area, which connections are still possible for high and very high power. A power supply area is the zone fed by one transformer station. The colour depends on the expected grid congestion in that area in 2035.

It is a forecast, not today. An orange area is not an area where the lights go out.

It is indicative and not binding. For a specific file, Fluvius can still find another solution, for example because of the Elia grid upstream or other factors.

Some companies panic and freeze a project the map does not even concern. Others see green, buy a building or order machines, and learn a year later that their address gets another answer.

It is about extra power on medium voltage. A high or very high power connection, which Fluvius calls a large-power connection, typically means medium voltage from 100 kVA. According to Fluvius, households are not affected, and the grid operator always keeps capacity for the low-voltage grid.

Small businesses are connected there too. On low voltage, demand grows through tens of thousands of small requests. On medium voltage, a single request for a very large power can change the free capacity of a whole area.

A workshop on 3 x 400 V that adds a machine may stay outside the map. The same workshop that has to move to medium voltage for that machine lands right in it. Our article on low voltage or medium voltage for a business explains where that line lies.

In June 2026, Voka reported that the Flemish majority parties had agreed to drop pure "first come, first served" in congestion areas. Low-voltage users and essential services would get the highest priority.

According to Voka, companies with a battery behind the meter could qualify too, as projects that reduce the load on the grid. Medium-voltage companies come in a second category. The regulator still has to turn this into rules.

What do orange, yellow and green mean for your expansion?

Orange means only flexible connections, yellow means flexible from 1 MVA of extra power, and green means classic connections are still possible. On the September 2026 map, most of Flanders is orange.

Colour Fluvius legend What it means for a request for extra power
OrangeFlexOnly flexible connections. How much flexibility depends on the expected congestion in the area
YellowFlex for very high power, fixed for high powerA request for 1 MVA or more of extra power gets a flexible connection
GreenFixed for high and very high powerClassic, permanent connections remain possible up to a total above 5 MVA. The effect of the upstream grid is not known yet

In Flanders, the flexible connection that Fluvius offers today is called Fall-Back Flex. You get the full power you asked for, but Fluvius may limit it temporarily at exceptional peaks. You can refuse it, but then your connection may wait until the grid is reinforced.

Our article on what to do when Fluvius refuses a heavier connection explains Fall-Back Flex in detail.

Important

Green is not a promise for your address: the upstream grid of Elia can still change the answer. Treat every colour as the question to ask, not as the answer.

How do you find your site on the map, step by step?

Download the latest map, find the area around your site, and write down the colour and the date. Then check it against your own numbers.

  1. Step 1: Open the Fluvius page with figures and maps and download the latest PDF. Check the date: an older copy may show another colour.
  2. Step 2: Zoom in on your site. The areas follow the transformer stations, not the municipal borders.
  3. Step 3: Note the colour and compare it with your request. How much extra power do you need, in kVA, and would it take you from low to medium voltage?
  4. Step 4: Look at the table of open files on the same page. It shows how busy the queue is.
  5. Step 5: Ask Fluvius for your own case. Only a request and an offer tell you what you get, when and on which terms.

Tip

Before you buy or rent a building, check its existing connection too: the kVA, the cabin and the peak history. Our article on checking the grid connection of a business building gives the full checklist.

What do the monthly Fluvius figures tell you about the queue?

They show how many large-power files are open, and at which stage.

Open files, 15 September 2026 Quote still to be made Quote sent Contract signed
Requests for a classic connection3357441,500
Requests with flexibility32784043

Fluvius adds a warning: "Quote still to be made" is a normal internal step, not a queue for the connection itself. The table covers all open files for high and very high power and industrial batteries since autumn 2025.

About 1,800 projects were waiting for a new or heavier connection in Flanders in June 2026, according to Voka. In December 2025, 181 requests for a connection to the high-voltage grid were still being studied, VRT reported.

Elia and Fluvius said they aim to give those companies clarity within two years. They also said that speculative requests block the queue for real projects.

So ask early, and ask for what you really need. A realistic request with a clear load profile fits more easily into the capacity that is left.

Is there a congestion map for Wallonia or Brussels?

No public colour map of this kind exists in Wallonia or Brussels today. In Wallonia, ORES says the situation varies by region and several zones already have a high risk of congestion.

ORES distinguishes two kinds of congestion. Local congestion sits at the Elia transformer station that feeds the ORES grid. Upstream congestion sits on the Elia transmission lines and reduces what that station can deliver.

Both limit new connections and upgrades above 56 kVA for business customers. Without a map, the study is your map. An orientation study is paid and not binding, and only gives you information.

Only the detail study officially starts your request and reserves your place in the queue for that Elia station. In June 2026, 1,066 connection requests were waiting for an answer at ORES, 161 of them in the Mons-La Louvière area. Our article on a business connection with ORES or RESA explains the steps, costs and the flexible connection above 250 kVA.

In Brussels, we found no public congestion map from Sibelga. Ask Sibelga directly with your address and the power you need, before you plan the project.

Can a battery or a semi-off-grid system let you grow in an orange area?

Often yes, because the map is about extra power from the grid, not about the power a battery delivers on your own site. The battery charges when the site is quiet and adds its power when the machines run. Plan on the power you can be sure of, and cover the rest yourself.

Your situation What usually works Watch out for
Low voltage, growth would push you onto medium voltageStay on your street connection and add a battery and solar panelsUp to 75.6 kVA with a semi-off-grid system
Medium voltage, short peaks above what you can getTake the connection on offer and cover the peaks with a batteryThe battery is sized on the peak and the energy per day
Medium voltage, flexible connection offeredAccept it and let a battery carry the site when Fluvius limits the powerAsk how often and how long a limitation can last
High power for many hours a dayAsk early, with a realistic load profile, and plan the reinforcementA battery only delays the problem

For companies and farms on a standard 3 x 400 V connection, a semi-off-grid system goes furthest. Solar panels and a battery carry the site, and an automatic transfer switch changes over to the grid when needed. It works up to 75.6 kVA, which is 3 x 400 V with 63 A.

A plant nursery in Jabbeke needed a heavier connection for a new irrigation pump; the proposal was medium voltage, at a high price. The semi-off-grid system let it keep its 3 x 400 V, 32 A street connection. That connection now charges a system that delivers 63 A to the pumps; variable speed drives start the heaviest pumps smoothly.

In Tielt, a farm would otherwise have needed medium voltage to expand. The battery system gives the site more power instead. It is expected to take only about 5% of its yearly use from the grid.

Above 75.6 kVA, a business battery does the same behind a medium-voltage connection, keeping your draw under the power you have and covering the rest. More power without a grid upgrade shows the calculation for one machine; the peak demand of a business explains how to read your peaks first.

Watch out

A battery does not create energy. If your site uses more energy in a day than the connection and your solar panels deliver, the battery empties and stays empty. Our article on a medium-voltage cabin or a battery compares the routes for larger sites.

Your site is in an orange area and needs more power? Tell us what you draw and plan; we tell you whether you can grow on your connection.

+32 494 36 37 91Contact usRequest a quote

Frequently asked questions

Is there grid congestion in Belgium today?

Not in Flanders: Fluvius says there is no actual grid congestion there today, only expected congestion for 2035. So an orange area does not mean power cuts. In Wallonia, ORES already sees a high risk of congestion in several zones.

How often does Fluvius update the congestion map?

Every month, around the 15th, together with the table of open files for high and very high power. Always check the date of the copy you use.

Can I use the Dutch capacity map for my site in Belgium?

No. The Dutch maps rank high in search results, but the capacity maps of Netbeheer Nederland and TenneT cover the Dutch grids only. In Flanders use the Fluvius map; in Wallonia and Brussels ask ORES, RESA or Sibelga.

Is the grid holding back your plans?

Tell us where your site is, what it draws today and what you want to add. One of our engineers will tell you whether you can grow behind your current connection, and what it changes for your planning.

  • Analysis and sizing. Where possible we first measure your consumption for a period, so the peaks and the energy per day are known.
  • Technical design. We compare your plan with the connection you have or can get. Then we tell you whether a battery, a semi-off-grid system or a heavier connection is the honest answer.
  • Installation and start-up.
  • Monitoring and ongoing support. You follow consumption, yield and the battery level in real time.

Contact usRequest a quote

Sources

  1. Fluvius: grid congestion figures and maps, update of 15 September 2026 (Dutch)
  2. Fluvius: grid congestion in Flanders, connection options per power supply area (PDF map, Dutch)
  3. Fluvius: congestion measures in Flanders (Dutch)
  4. Fluvius: expected grid congestion, what it means for your company
  5. Fluvius: frequently asked questions on grid congestion (Dutch)
  6. Fluvius: are you a large-power customer? (Dutch)
  7. Fluvius for local government: solving grid congestion flexibly, 11 June 2026 (Dutch)
  8. Fluvius press release, 9 January 2024: capacity guide for businesses (Dutch)
  9. Voka, 23 June 2026: Flanders agrees a priority framework for grid congestion (Dutch)
  10. VRT NWS, 11 December 2025: 181 companies wait for a connection to the high-voltage grid (Dutch)
  11. Elia open data: Congestion Risk Indicator per electrical zone
  12. ORES: access to power (French)
  13. ORES: FAQ on access to power (French)
  14. ORES: interactive map of inverters that trip (French)
  15. Walloon Parliament, written question 410 (2025-2026), answer of 22 June 2026 (French)
  16. Netbeheer Nederland: capacity map of the Dutch grids (Dutch)

About the author

YouPower. YouPower, based in Zele, has designed, sized and installed battery and off-grid energy systems for businesses, farms and homes since 2018. Victron Energy Certified Partner, own engineering office, open-source control and in-house battery recycling. More about YouPower


www.Youpower.be uses cookies to improve your experience on this site. By continuing to browse, you consent to our use of cookies.