Hotel grid connection delayed? Open with the power you can get now; solar panels and a battery supply the rest until the full connection is ready. Up to 75.6 kVA, a semi off-grid system runs the hotel on sun and battery, using the grid only when needed, like a generator.
Permit, plans and contractor ready, for a new hotel, an extension or a new wing, and the grid operator has no capacity? Or it offers part of the power years from now, while the bank asks about the opening date.
We are currently equipping a hotel fully with solar panels and batteries ourselves.
Why is a hotel grid connection refused or delayed in Belgium?
Because the local grid, or the transformer station behind it, is already full. A hotel asks for a lot of power at once. When the station has no room left, the grid operator cannot connect the full power until it has built more capacity.
In Transinne (Libin), the Van der Valk group had its permit for a 113-room hotel, but the Elia station in Recogne was saturated, L'Avenir reported. In March 2026 a member of the Van der Valk family told La DH that "a solution will be found using batteries". Van der Valk is not our customer; we cite this as news.
Walloon grid operators received 1,167 connection study requests in 2025, against 736 in 2023, La DH reported. Industrial electrification, batteries and fast chargers drive the growth. ORES warns that designing, permitting and building new grid installations "sometimes takes several years".
Connection study requests to the Walloon grid operators
In Flanders, Fluvius says there is no actual grid congestion today, and it takes preventive measures for large users. There a hotel more often hits a connection too small for new loads, or a quote for a medium voltage cabin. Our article on what to do when a heavier connection is refused or delayed explains the Fluvius procedure and its flexible connection.
Tip
Ask for a detailed connection study as soon as your project is defined, as ORES also advises. It tells you how much power you get, and when, so you can size the bridge. Taking over an existing building? Then check the grid connection of the building before you buy or rent it.
How much power does a hotel need, and at what time of day?
A hotel needs its highest power at breakfast and in the evening, not at noon. Solar panels deliver most at noon, when many guests are out and the kitchen is quiet.
A typical hotel day and where the power comes from
- Kitchen: ovens, dishwashers and cold rooms, with the peak at breakfast and dinner.
- Heating, cooling and hot water: with a heat pump, this becomes the largest electrical load. Hot water for showers peaks in the morning.
- Laundry, lifts, wellness: a sauna or pool heating adds a long, steady load.
- Chargers for guests: most guests arrive in the evening and want to charge overnight.
In the Netherlands, Hotel The Florian in Hoofddorp had a contracted power of 137 kW, and the grid operator refused more. With 30 kW of solar panels, a 40 kW / 50 kWh battery and an energy management system, it stayed within its connection. During construction it still went over the limit once more and got a second warning.
How do solar panels and a battery bridge the wait for the final connection?
The battery covers everything above the power the grid can give you today. It fills up from the solar panels and in quiet hours, and empties when the hotel peaks. The building sees the full power; the grid only sees a smooth, lower load.
How a hotel opens before its full connection
Waiting is the most expensive option: every month of delay is a month of empty rooms and loan interest. A rented diesel generator burns fuel day and night, makes noise next to guest rooms and still needs a plan for the peaks. A battery sized to replace the grid completely pays for capacity you only need until the cable arrives.
Where the grid said no, we work the same way. A plant nursery in Jabbeke had 3 x 400 V, 32 A and needed a heavier connection for a new irrigation pump.
It got a costly medium voltage proposal. With a semi off-grid system, it kept its street connection and uses it only as a charger for a stronger 63 A supply. A farm in Tielt avoided medium voltage the same way.
| Option | What it means for the hotel | Our verdict |
|---|---|---|
| Wait for the full connection | No opening, or a partial opening, until the grid is reinforced | Only if the date is close and certain |
| Rented diesel generator | Full power from day one, fuel and maintenance every day | A stopgap for weeks, not for years next to guest rooms |
| Small connection + solar + battery (semi off-grid) | Grid as charger and back-up, battery covers the peaks | The best fit up to 75.6 kVA |
| Flexible or partial connection + business battery | Firm power from the grid, battery covers the rest | The fit for larger hotels |
| Fully off-grid: solar + battery + generator | No connection at all, generator for dark weeks | When no connection is possible on the site |
No connection at all on your plot? A rental company in Zele got none from the grid study and runs fully off-grid on solar panels, a battery and a generator. The generator covers about 5% of the yearly demand.
Our article on building without a grid connection explains this last resort. How the two work together is in a generator with a battery.
What does a flexible connection in Wallonia mean for a hotel?
A flexible connection gets you on the grid sooner, but not with full power at all times. ORES offers it for connections above 250 kVA. Part of the power is firm and always there; the other part can be limited when the grid is congested.
The Walloon Parliament adopted the decree on flexible offtake in December 2025. ORES calls the flexible contract a transitional solution while the transmission grid is reinforced. ORES itself lists storage batteries, self-consumption and smart load control as ways to deal with limited power.
The regulator CWaPE approved the new contract models of ORES and RESA on 25 June 2026. But until 31 December 2027, it notes, only the firm capacity will actually be made available.
For a hotel, the firm part is the number that counts. If it covers the night and the daytime load, a battery covers the breakfast and evening peaks. When the flexible part becomes usable, the battery simply works less.
Watch out
Under 250 kVA, a semi off-grid system fills exactly the gap between the connection you have and the power you need. Weighing a cabin against a battery? Our article on grid extension cost versus a battery compares the two; in Londerzeel avoiding the cabin saved at least 60,000 euro.
How big should the battery for a hotel be?
The battery must cover the gap between your peak and the power you get, for as long as that peak lasts. A short breakfast peak needs less storage than a long evening of kitchen, sauna and guest chargers. Work through these questions with your engineering firm.
What power do you get, and when?
The answer from the connection study: power now, firm power, and the expected date of the final connection.
What is your peak, and how long does it last?
A new building has no meter yet. Use the load estimate of the engineering firm and list the big loads: kitchen, heat pump, hot water, lifts, wellness.
Which loads can wait?
Laundry at night, pool heating at noon, chargers spread over the night. Every kW you move lowers the battery you need.
What must never stop?
Reception, emergency lighting, cold rooms, lifts. A battery that runs as an island keeps them going in a power cut too.
How do you get through the construction phase?
The site needs power before the hotel does: see our article on the building-site battery. Does the building-site connection itself come too late? Read what to do when your construction site connection comes too late.
Blocked by the grid with an opening date to keep? Call us or send a message.
What happens to the hotel battery once the final connection arrives?
It keeps working in a different role, so we size it for the years after the bridge as well. A battery bought only to bridge a wait would be expensive; one that stays useful pays for itself over many more years.
- Back-up for guests: in a power cut, the battery keeps reception, lighting, lifts and cold rooms running. Our guide to emergency power for a business compares battery, UPS and generator.
- Lower peaks: in Flanders, the capacity tariff is based on your highest quarter-hour peaks, so shaving the breakfast peak lowers that cost. Our article on calculating the capacity tariff shows how.
- Market prices: with a dynamic contract, the battery charges when power is cheap and discharges when it is expensive. See a dynamic energy contract with a business battery.
- Room to grow: a new wing, a spa or more guest chargers, without asking the grid for more power right away.
Our monitoring software shows in real time how much solar power the hotel uses directly and how much goes into the battery. Once the final connection is there, it also tells you which role pays most.
Our verdict
Solar panels and a battery are the right bridge when the wait is long or unknown, and the battery stays useful afterwards. When the final connection is only a few weeks away, a rented generator for the gap is cheaper. A battery on a site full of guests needs the right room or distance, which our article on business battery safety explains.
Frequently asked questions
Can a hotel run completely without a grid connection?
Technically yes, with enough solar panels, a battery and a generator for the dark weeks. For a hotel with kitchens and heat pumps that is a large system. Keeping whatever connection is available as a back-up source usually makes more sense.
Is a diesel generator a good bridge for a hotel?
For a few weeks, yes. A battery lets a smaller generator run only when it is really needed, or not at all.
Can a hotel add EV chargers without a grid upgrade?
Yes, if the charging is managed and spread over the night, and a battery covers the evening arrivals. Our article on chargers without a heavier connection explains the options.
Does a flexible connection exist in Flanders too?
Yes. Fluvius uses flexible connections to connect faster in zones with a congestion risk, mainly for large users.
Want to open your hotel on time, despite the grid?
Tell us what the grid operator offered, what the hotel needs and when you want to open. One of our engineers tells you how much of the gap solar panels and a battery can close. You also learn what stays useful after the final connection.
- Step 1: Analysis and sizing. We look at the power the grid offers, the load estimate and the peaks. For an existing hotel we can first monitor the consumption for a short period.
- Step 2: Technical design. We choose the battery, the inverter power, the solar panels and, where needed, a back-up generator.
- Step 3: Installation and start-up.
- Step 4: Monitoring and support.
Every installation is calculated on your consumption, your production and your future plans. Our semi off-grid systems are the starting point for smaller hotels; larger sites get a business battery up to 1 MW.
Sources
- L'Avenir, 27 September 2025: the Van der Valk hotel project in Transinne on hold for lack of electricity
- L'Avenir, 22 October 2025: saturated grid in Wallonia, Cécile Neven launches the flexible connection
- La DH, 23 March 2026: La Barrière de Transinne and the Van der Valk hotel project
- La DH / Belga, 11 December 2025: hundreds of companies blocked at the doors of the Walloon grid
- ORES: access to power in Wallonia
- ORES: what is a flexible connection?
- CWaPE: approval of the flexible offtake contract models (June 2026)
- Walloon Government (Minister Neven): the flexibility decree, 18 December 2025
- Fluvius: what is grid congestion?
- Solar365: Hotel The Florian built a local grid to be able to open